Project Name:
| Hung Fuk Estate - Hung Fuk Shopping Centre, Hung Fuk Estate Ancillary Facilities Block, Hung Foon House, Hung Yan House, Hung Hei House, Hung Lok House |
Scope Of Work:
| Electrical and FS System |
Contract Period: |
2012/12 - 2015/05 |
Client: |
Hong Kong Housing Authority |
Architect: |
Hong Kong Housing Authority |
Consultant: |
Hong Kong Housing Authority |
Quantity Surveyor: |
Langdon & Seah HK Ltd |
Main Contractor: |
Hsin Chong Construction Co Ltd |
Project Description: |
- Total Construction Floor Area: 136,560 m2
- Commercial Centre & Ancillaty Facilities Block
- Total: 4 Blocks with 2,097 Domestic Flats
Electrical Installation:
- 11 x 1500kVA Transformer
- 3 x 280kVA, 1 x 250kVA & 1 x 480kVA FSI Generator Set
FS Installation:
- 2,700 nos. Sprinkler Head
- 130 nos. AFA Detector |