Macau
Project Name: Wynn Palace Macau - Hotel Tower
Scope Of Work: MVAC System
Contract Period: 2012/11 - 2016/08
Client: Wynn Design Development
Architect: Wong & Ouyang (HK) Ltd
Consultant: JBA Consulting Engineers
Quantity Surveyor: -N/A-
Main Contractor: Leighton Contractors (Asia) Ltd
Project Description: - Total Construction Floor Area: 432,000 m2
- The Wynn Palace is located at Cotai, Tai Pa including around 1,700 guestrooms, some villas, restaurants, shopping mall and casino. Our works are included of supply, installation, testing & commissioning of the completed HVAC system for the hotel tower with some major systems:

MVAC Installation:
- Chiller Water Pipe System
- Heating Water Pipe System
- Centralized Primary Air Handling Unit System
- Centralized Exhaust Air System for Bath Rooms
- Fan Coil Units for Suites / ELV Rooms / UPS Rooms / TR Rooms / Lift Machine Rooms / Main Switch Room, etc.
- Smoke Exhaust & Staircase Pressurization System