Project Name:
| Wynn Palace Macau |
Scope Of Work:
| Central Chiller Plant, Site-wide BMS and Dry Fire System |
Contract Period: |
2014/01 - 2016/08 |
Client: |
Wynn Design Development |
Architect: |
Wong & Ouyang (HK) Ltd |
Consultant: |
JBA Consulting Engineers |
Quantity Surveyor: |
-N/A- |
Main Contractor: |
Leighton Contractors (Asia) Ltd |
Project Description: |
- Total Construction Floor Area: 432,000 m2
- A 29-storey hotel with 1,700 nos. luxury guest rooms on top of a four level above grade and one level below grade podium.
- The podium house with dining, retail, convention, spa, entertainment, parking and related support facilities.
Central Chiller Plant Installation:
- 8 x 8,440kW Water Cooled Chiller
- 8 x 10,614kW Cooling Tower
- 5 x 1,311kW Heat Pump
- 3 x 3,920kW Hot Water Boiler
- 2 x 980kW & 1 x 2,385kW Steam Boiler
- Site-wide BMS System
FS Installation:
- 25,540 nos. AFA & Associated Monitoring Point |