Hong Kong
Project Name: DCS Phase III (Package D) - Electrical and Mechanical Installation
Scope Of Work: MVAC and EL System
Contract Period: 2019/01 - 2023/01
Client: Electrical and Mechanical Services Department
Architect: -N/A-
Consultant: Ove Arup & Partners Hong Kong Ltd
Quantity Surveyor: -N/A-
Main Contractor: -N/A-
Project Description: MVAC System :
- 6 x 5000 RT HV Water Cooled Chiller (Northern Plant)
- 2 x 2500 RT HV Water Cooled Chiller (Northern Plant)
- 4 x 5000 RT HV Water Cooled Chiller (Southern Plant)
- 8 x 5231 kW Cooling Tower (Northern Plant)
- 6 x 524 l/s Chilled Water Pump (Northern Plant)
- 2 x 262 l/s Chilled Water Pump (Northern Plant)
- 4 x 524 l/s Chilled Water Pump (Southern Plant)
- 4 x 530 l/s Condensing Water Pump (Northern Plant)
- 5 x 820 l/s Sea Water Pump (Sea Water Pump House)
- 1 nos. TBS (Sea Water Pump House)
- Expand the existing Chlorination system (Sea Water Pump House)
- 4 x 8000 kW PHX installation (Substation 1F2 - AirSide)
- 1 x 3000 kW PHX installation (Substation 1F2 - AirSide)

Electrical System :
- 4 x 2000kVA Transformer (Northern Plant)
- 2 x 2000kVA Transformer (Southern Plant)
- Extend the existing LVSB (Northern & Southern Plant)
- Addition of New LVSB (Northern Plant)
- Addition of New Lighting / Power / ELV Points at around 200 nos (Northern, Southern & Sea Water Plant)