| Project Name:
| Artisan House |
| Scope Of Work:
| EL & ELV and PD System |
| Contract Period: |
2016/01 - 2018/09 |
| Client: |
New World Development Co Ltd |
| Architect: |
Cheung Kong-Yeung Architects Ltd |
| Consultant: |
P&T (M&E) Ltd |
| Quantity Surveyor: |
N/A |
| Main Contractor: |
Kaden Construction Ltd |
| Project Description: |
- Total Construction Area: 8,710 m2
- 1 Tower with 250 residential flats
- 1 No. of Clubhouse
Electrical Installation:
- 1 x 2000kVA transformer
- 1 x 400kVA FSI Generator Set
PD Installation:
- 4 sets Transfer Water Pump
- 2 sets Booster Water Pump |