Project Name:
| K11 Atelier King's Road |
Scope Of Work:
| PD and ELV System |
Contract Period: |
2016/12 - 2019/09 |
Client: |
New World Development Co Ltd |
Architect: |
P&T Architects and Engineers Ltd |
Consultant: |
Ove Arup & Partners Hong Kong Ltd |
Quantity Surveyor: |
N/A |
Main Contractor: |
New World Construction Co Ltd |
Project Description: |
- Total Construction Floor Area: 45,290m2
- 28 storeys comprises of 22 office floors & 3 basement floors for carpark
- G/F to 2/F Shops and Exhibition Space
PD Installation:
- 3 sets Transfer Water Pump
- 4 sets Booster Water Pump
- 9 sets Submersible Water Pump
ELV System:
- Network Structured Cabling System
- 200 nos. CCTV
- 132 nos. of Access Point for WIFI System
- 109 nos. of Card Reader Door Control System
- 286 nos. of Loud Speakers for PA System
- 80 nos. of DDC Panel for BMS System |