Project Name:
| Altissimo |
Scope Of Work:
| Plumbing & Drainage System |
Contract Period: |
2018/07 - 2020/08 |
Client: |
Country Garden Properties (Hong Kong) Limited |
Architect: |
Lu Tang Lai Architects Ltd |
Consultant: |
WSP Hong Kong Ltd |
Quantity Surveyor: |
Arcadis Hong Kong Ltd |
Main Contractor: |
China Overseas Building Construction Co Ltd |
Project Description: |
- Total Construction Floor Area: 36,000 m2
- 4 Towers of 12 to 14 storeys and 1 Tower of 4 storeys with 547 Residential Units
- 1 Storey of Carpark at Basement & Clubhouse
PD System:
- 46 Sets of Booster Water Pump
- 45 Sets of Submersible Pump
|