Project Name:
| Pak Tin Estate Phase 11 - Long Tin House, Ching Tin House, Commercial Centre |
Scope Of Work:
| Electrical Installation |
Contract Period: |
2017/05 - 2021/06 |
Client: |
Hong Kong Housing Authority |
Architect: |
Hong Kong Housing Authority |
Consultant: |
Hong Kong Housing Authority |
Quantity Surveyor: |
Hong Kong Housing Authority |
Main Contractor: |
Chun Wo Construction and Engineering Co., Ltd. |
Project Description: |
Total Construction Floor Area: 54,975m2
- 2 Blocks with 1,088 residential flats
- B/F of Non-domestic area for shopping commercial centre
- 1/F of Long Tin House for kindergarten
Electrical Installation:
- 4 x 1500kVA Transformers for Residential
- 1 x 1500kVA Transformers for Non-domestic
- 1 x 450KVA FSI Generator Sets for Residential
- 1 x 800kVA FSI Generator Sets for Residential and B/F Non-domestic |