Project Name:
| Emerald Green |
Scope Of Work:
| EL, FS, PD and MVAC System |
Contract Period: |
Dec. 1997 to Dec. 1998 |
Client: |
New World Development Co Ltd |
Architect: |
Andrew Lee King Fun & Associates Architects Ltd |
Consultant: |
Consolidated Consulting Engineers Ltd |
Quantity Surveyor: |
N/A |
Main Contractor: |
Hip Hing Builders Co Ltd |
Project Description: |
- Total Construction Floor Area: 44,827 m2
- 5 blocks 24 storeys residential with 672 flats
- 1 no. Swimming Pool & 2 nos. of Water Feature
Electrical Installation
FS Installation:
- 2,339 nos. Sprinkler Head
- 380 nos. AFA Detector
PD Installation:
- 20 sets Transfer Pump
- 10 sets Booster Pump
MVAC Installation:
- 1,500 nos. single & multi split type AC unit
- 1 x 309kW VRV type AC unit
|