Project Name:
| LOHAS Park - The Capitol |
Scope Of Work:
| Electrical and PD System |
Contract Period: |
2006/08 - 2009/06 |
Client: |
Cheung Kong (Holdings) Ltd |
Architect: |
Hsin Yieh Architects & Engineers Ltd |
Consultant: |
Parsons Brinckerhoff (Asia) Ltd |
Quantity Surveyor: |
WT Partnership (HK) Ltd |
Main Contractor: |
Able Engineering Co Ltd (Carcass Contractor) |
Project Description: |
- Total Construction Floor Area : 136,240 m2
- 5 Towers with total 2,096 flats
Electrical Installation:
- 18 x 1500kVA Transformers
- 1 x 350kVA Generator Set
- 1 x 1000kVA Generator Set
- 1 x 1400kVA Generator Set
PD Installation:
- 25 sets Transfer Pumps
|