Project Name:
| NWS Kwai Chung Logistics Centre |
Scope Of Work:
| EL, PD, FS and MVAC System (E&M Package) |
Contract Period: |
2009/09 - 2011/08 |
Client: |
NWS Holdings Ltd |
Architect: |
Aedas Ltd |
Consultant: |
Maunsell E&M Consulting Ltd |
Quantity Surveyor: |
N/A |
Main Contractor: |
Hip Hing Construction Co Ltd |
Project Description: |
- Total Construction Floor Area: 64,500 M2
- 5 Storeys Warehouses & 7 Storeys Offices
Electrical Installation:
- 7 x 1500kVA Transformers
- 1 x 2000kVA FSI & 1 x 1000kVA NFSI Generator Sets
PD Installation:
- 5 sets Booster Pumps
- 5 sets submersible Pumps
FS Installation:
- 23,000 nos. Sprinkler Head
- 1,100 nos. AFA Detector
MVAC Installation:
- 2 sets of VRV system for Lift Lobby & Office Area
- Ventilation system for L & UL area, Toilets & Office
- 4 sets of Staircases Pressurization System
|