Project Name:
| Chong Hing Bank Centre |
Scope Of Work:
| EL and PD System |
Contract Period: |
2005/06 - 2006/09 |
Client: |
Right Way Investment Ltd |
Architect: |
P&T Architects and Engineers Ltd |
Consultant: |
P&T (M&E) Ltd |
Quantity Surveyor: |
Widnell Ltd |
Main Contractor: |
Hip Hing Construction Co Ltd |
Project Description: |
- Total Construction Floor Area : 12,400m2
- 28 storeys office
- G/F to 3/F banking halls and offices from 4/F to 26/F
Electrical Installation:
- 2 x 1,500kVA Transformers
- 1 x 650kVA NFSI and 1 x 350kVA FSI Generator Sets
PD Installation:
- 3 Set Transfer Pumps
- 4 Set Submersible Pumps |