Hong Kong
Project Name: Kai Tak Stage 2 Infrastructure Works for Developments at the Southern Part of the Former Runway
Scope Of Work: EL System
Contract Period: 2017/04 - 2020/09
Client: Civil Engineering and Development Department
Architect: A. Lead Architects Ltd
Consultant: WSP Parsons Brinckerhoff
Quantity Surveyor: AECOM Asia Co Ltd
Main Contractor: CEC - CCC Joint Venture
Project Description: - Total Construction Floor Area : 50,000 m2
- Realignment and widening of the existing single 2-lane Shing Fung Road to a dual 2-lane distributor road of about 1.4 km long
- The elevated landscaped deck connection with lifts and staircases for the Metro Park in the north to the Kai Tak Cruise Terminal, Tourism Node and Runway Park in the south of the former runway