Project Name:
| Harbour Glory & Hotel Alexandra |
Scope Of Work:
| PD System |
Contract Period: |
2016/05 - 2020/05 |
Client: |
CK Asset Holdings Limited |
Architect: |
LWK & Partners (HK) Ltd |
Consultant: |
Meinhardt (M&E) Ltd |
Quantity Surveyor: |
Davis Landgon KPK (HK) Ltd |
Main Contractor: |
Aggressive Construction Co Ltd (Carcass) |
Project Description: |
Total Construction Floor Area : 103,590m2
- 6 Towers with 378 residential flats
- 1 Block of Hotel includes 840 Guest Rooms
- 4 Layer Basement include:
B1 Hotel Entrance Lobby & Club House
B2 Residential Club House & Carpark
B3 & B4 Plant Room & Carpark
PD Installation:
- 15 sets of transfer water pumps
- 11 sets of booster water pumps
- 64 sets of submersible pumps
- 3 sets of priming pumps |