Medical
Project Name: HKSH Eastern Medical Centre
Scope Of Work: MVAC Installation & Electrical Installation
Contract Period: 2017/08 - 2022/04
Client: HKSH AKN Ltd.
Architect: Ronald Lu & Partners (Hong Kong) Ltd.
Consultant: Mott Macdonald Hong Kong Ltd.
Quantity Surveyor: Rider Levett Bucknall Ltd.
Main Contractor: N/A
Project Description: EL Installation
- LV Switchboards receiving supply from HEC 22kV HV Panels through HKSH MV Switchboards and Transformers (1 x 630kVA, 1 x 1000kVA & 1 x 2000kVA Transformers at B1/F and 2 x 1600kVA, 2 x 2000kVA Transformers at 20/F)
- 1 x 1250kVA Genset (FSI)
- 2 x 1250kVA Genset (NFSI)
- 2 x 200kVA (1+1) UPS system for Engineering
- 2 x 200kVA (1+1) UPS system for IT
- 4 x 25kVA (Duty) & 25kVA (Redundancy) (4+1) UPS System for Proton Therapy
- 6 x 25kVA (Duty) & 25kVA (Redundancy) (6+1) CBS for FSI lighting

MVAC Installation
Supply and installation of various major systems to the medical centre : -
Chilled water system with
- 4 x 1407kW Water-cooled chiller with chilled water pumps
- 3 x 2744kW Cooling towers with condensing water pumps
Heating water system with
- 2 x 356kW Heat pump with chilled water pump and heating pumps
- 1 x 1000L electric boiler
Hot water system with
- 3 x 3000L electric boiler
- 2 x compact units
- 2 x heat exchanger with hot water circulation pump
Cooling water system with
- 2 x heat exchanger
- 2 x cooling water pumps
Air compression system with
- 2 x 2240L/min air compressor
- 2 x 1000L air tank
2 sets Staircase pressurization system, each with
- 2 x SPF
- 2 x SRF
Smoke extraction system with
- 2 x MAF
- 10 x SEF