Project Name:
| Immigration Headquarters |
Scope Of Work:
| HVAC, EL and ELV, FS, PD System (Design & Build) |
Contract Period: |
2019/06 - 2023/09 |
Client: |
Architectural Services Department |
Architect: |
P&T Architects and Engineers Ltd |
Consultant: |
J. Roger Preston Limited |
Quantity Surveyor: |
C.S. Toh & Sons & Associates Ltd |
Main Contractor: |
Hip Hing Engineering Co Ltd |
Project Description: |
- Total Construction Area: 139,000m2
- One 18-storey Main Tower comprising of North Wing and South Wing, one 18-storey Security Tower and a single-storey basement carpark
Tower 1 (T1)
- G/F to 16/F (Security Tower)
Tower 2 (T2N & T2S)
- G/F to 16/F (Main Tower)
MVAC Installation:
- 5 x 3220kW (5 x 920TR) Water Cooled Chiller
- 1 x 3220kW (1 x 920TR) Water Cooled Heat Recovery Chiller
- 2 x 2150kW (2 x 610TR) Water Cooled Oil Free Chiller
- 3 x 1450kW (3 x 412TR) Air Cooled Chiller
- 2 x 1500kW (1 x 430TR) Water to Water Heat Pump
- 6 x 3800kW + 2 x 3150kW Cooling Tower
- 20 nos. Solar Hot Water Collection Panel
- 94 nos. AHU & 11 nos. PAU
- 48 nos. CRAC unit
Electrical Installation:
- 12 x 2000kVA Transformers
- 4 x 2000kVA Generator Set
- 3 x 2250kVA Generator Set
- 1600kVA UPS (15 min. back-up) for Data Centre
- 740kVA UPS (30 min. back-up) for user equipments
- 12kVA UPS (10 min. back-up) for key management authority
- 101.37 kW/year Produced Energy by PV System with 186 PV modules
ELV Installation:
- 1576 x CCTV Security
- 1658 x Access Control
- 845 x Public Address
- 3453 Telephone Point
- 265 x Display Unit
- 656 x Broadcast Reception Points
- 146 x walkie talkie
- 4 sets walk through detector
- 5 sets X Ray Scanner
FS Installation:
- 36,000 nos. Sprinkler Head
- 2500 nos. AFA Detector
- 40 sets Novec1230 System
- 2 sets Sprinkler Pump
- 2 sets FH/HR Pump
- 2 sets FS Intermediate Booster Pump
- 1 set Street Fire Hydrant Pump
PD Installation:
- 14 sets booster water pump
- 15 sets submersible pump
- 15 sets transfer pump |